Magazines
Subscriber Services
Writy.
  • Home
  • Park News
  • Buyer’s Guide
  • PIE Event Home
    • PIE 2026 Event
    • PIE 2025 Event
      • PIE25 Attendee Registration and Travel Details
      • PIE25 Agenda and Content Details
      • PIE25 Exhibitor & Sponsor Partnerships
      • PIE25 ParkFlix Film Festivial
      • Contact PIE25
  • Conference Companion
  • Segments
    • Higher Education
    • Municipal
    • Airport
    • Valet
    • Medical
    • Events
    • Commercial
    • Retail
    • Hospitality
  • Technologies
    • Gated
    • Ungated
    • Enforcement
    • Payments
    • Permits
    • Vehicle Detection
    • Wayfinding and Occupancy
    • Curb Management
    • Valet
    • Events
    • EV Charging
    • Analytics
    • Consumables
    • Lighting
  • Suppliers
    • Private Operators
    • Consultants
    • Engineers
    • Architects
    • Financial
    • Insurance
    • Mergers and Acquisitions
  • Industry Resources
    • Subscribe to Parking Today
    • Advertise with Us
    • Magazines
    • Industry Events
    • Conference Companion
    • Dealers, Installers & Suppliers – Listings
    • Industry News
    • Parking Jobs Network & RFP/RFQ’s
    • Associations
    • Podcast Network
    • Next Level – Webinar
    • Contact
No Result
View All Result
Writy.
  • Home
  • Park News
  • Buyer’s Guide
  • PIE Event Home
    • PIE 2026 Event
    • PIE 2025 Event
      • PIE25 Attendee Registration and Travel Details
      • PIE25 Agenda and Content Details
      • PIE25 Exhibitor & Sponsor Partnerships
      • PIE25 ParkFlix Film Festivial
      • Contact PIE25
  • Conference Companion
  • Segments
    • Higher Education
    • Municipal
    • Airport
    • Valet
    • Medical
    • Events
    • Commercial
    • Retail
    • Hospitality
  • Technologies
    • Gated
    • Ungated
    • Enforcement
    • Payments
    • Permits
    • Vehicle Detection
    • Wayfinding and Occupancy
    • Curb Management
    • Valet
    • Events
    • EV Charging
    • Analytics
    • Consumables
    • Lighting
  • Suppliers
    • Private Operators
    • Consultants
    • Engineers
    • Architects
    • Financial
    • Insurance
    • Mergers and Acquisitions
  • Industry Resources
    • Subscribe to Parking Today
    • Advertise with Us
    • Magazines
    • Industry Events
    • Conference Companion
    • Dealers, Installers & Suppliers – Listings
    • Industry News
    • Parking Jobs Network & RFP/RFQ’s
    • Associations
    • Podcast Network
    • Next Level – Webinar
    • Contact
No Result
View All Result
Writy.
No Result
View All Result

PHASE 1, Finished

by parkingtodaystaff
November 1, 2024
in Airport, Architects, Consultants, Enforcement, Engineers, EV Charging, Financial, Gated, License Plate Recognition LPR, Lighting, Payments, Private Operators, Vehicle Detection
PHASE 1, Finished

The first phase of the new 5-level Terminal 1 Parking Plaza at the San Diego International Airport began operations in August

 

By Michael Pendergrass

You might also like

Moving from Silos to Systems: The Case for Integrated Digital Parking Management

Moving from Silos to Systems: The Case for Integrated Digital Parking Management

May 29, 2025
A Garage that Shines

A Garage that Shines

May 29, 2025

 

In late August, phase 1 of the 5-level Terminal 1 (T1) Parking Plaza at the San Diego International Airport opened to the public. Comprising more than 2,800 stalls, the new facility includes advanced technology to enhance the parking experience for users, a carefully designed configuration that expedites traffic flows in and out of the garage, as well as an innovative stormwater management system and other sustainable features.

 

Response to growth

In late August, phase 1 of the 5-level Terminal 1 Parking Plaza at the San Diego International Airport opened to the public. 
PHOTOS COURTESY OF WATRY DESIGN

Since its construction in 1967, San Diego International Airport’s Terminal 1 has grown from serving 2.5 million passengers to more than 12 million. In response to this growth, the San Diego County Regional Airport Authority — the independent agency that manages the airport’s day-to-day operations — is transforming T1 with an entirely new facility that will offer more gates, a new passenger concourse, an improved roadway system, and a new parking plaza with more than 5,000 parking stalls. When completed, the 5-level T1 Parking Plaza will span 2 million square feet.

 

Because an existing roadway passes through the footprint for the new parking facility, a new road needed to be constructed before the existing one could be demolished. This necessity, combined with other construction logistics associated with the T1 replacement, meant that only the western half of the parking facility site would be available for construction initially. Therefore, the parking plaza was designed to be delivered in two phases. The recently completed phase 1 is a fully functioning facility that does not depend on features, systems, or elements of phase 2, which will add an additional 2,398 stalls.

 

Phase 1 was delivered by means of the design-build approach. The construction company Swinerton, Inc., was the design-builder, with the architecture firm Gensler as the design architect. The parking design company Watry Design, Inc., served as the architect and structural engineer of record for the project.

 

Key design details

 

In keeping with its goal to offer travelers an exceptional parking experience, the authority enables passengers to reserve parking in advance via the airport’s website. Sustainable-minded customers can purchase a carbon offset along with parking, with each $5 purchase offsetting 1,000 miles of flying.

Each level is color coded to help
passengers remember where they parked.
PHOTOS COURTESY OF WATRY DESIGN

 

T1 Parking Plaza incorporates an elevated technology experience that provides real-time parking information that helps guide users to an available space. Upon a visitor’s arrival, a license plate recognition system recognizes the vehicles of passengers who reserved parking in advance. Alternatively, passengers can use a QR code to gain entry. Passengers who did not reserve a space can go ticketless by scanning a credit card on entry and using the same card when exiting. Pay-on-foot kiosks are also available near the elevators.

 

Passengers looking to park have flights to catch and ticketing and security lines to navigate. Therefore, an important design consideration entailed expediting traffic flow in and out of the structure. To keep traffic moving smoothly, drivers enter and navigate through the structure by means of a series of cascading speed ramps that circulate cars quickly through the structure. A separate speed ramp directs exiting vehicles out of the structure, mitigating congestion between arriving and exiting drivers. Drive aisles are also oriented from north to south, creating a natural separation between vehicles entering from the north and pedestrians heading south toward the terminal.

 

Sensors over each parking space inform dynamic signage that displays real-time parking availability at each level and aisle by aisle. Once drivers turn down a parking aisle, LED lights help identify empty spaces. This system enables travelers to swiftly find a parking space without endless circling and idling.

 

Once on foot in the parking facility, passengers are drawn by expansive lightwells to the elevators and guided to the terminal across the street. During the day, the lightwells draw natural light and ventilation into the large structure. The lightwells include landscaped plazas that feature catenary lighting to create a lively atmosphere in the evenings.

 

Additional amenities such as vending machines and luggage carts are also available. When drivers depart, tire inflation stations are available free of charge to those
in need.

 

Going for gold

 

In certain key ways, the design of the T1 Parking Plaza borrowed from that of its successful predecessor, the Terminal 2 Parking Plaza, which opened in 2018. For example, the Terminal 2 Parking Plaza includes an innovative stormwater management system that collects and reuses rainwater from the facility's roof. To this end, a 100,000-gallon underground storage system collects the rainwater, while a treatment system beneath the bottom level of the structure cleanses and sends the water to the airport’s central utility plant.

Lightwells bring light into the structure and guide passengers towards Terminal 1.
PHOTOS COURTESY OF WATRY DESIGN

Each day, the central utility plant uses nearly 30,000 gallons of water to manage the temperature in the airport terminals. Thanks to its stormwater management system, the airport reuses nearly 2 million gallons of rainwater annually to feed the central utility plant, decreasing the volume of potable water that must be used for this purpose.

 

The T1 Parking Plaza incorporates a similar, but much larger, system for capturing, treating, and reusing roof runoff. Such a system is currently in operation as part of phase 1, while a similar system to be added as part of phase 2 will connect to it once it is complete next year. In total, this combined system will have the capacity to capture, treat, and reuse more than 39 million gallons of roof runoff annually.

In other sustainable design features, the new parking plaza will have more than 30 electric vehicle (EV) charging ports as of fall 2024. Upon full build out, 5% of the total parking stalls will provide EV charging, while another 5% of stalls will be capable of offering it in the future. EV owners can pay for charging at designated payment stations or via app. More than 500 stalls are reserved for EVs and other clean vehicles, those that use alternative fuels, and those that are used for carpools.

 

These and other sustainable features, including drought tolerant landscaping and efficient lighting, will contribute to efforts to have the overall project certified as a Parksmart Gold level facility as part of the Parksmart program for certifying high-performing, sustainable garages.

 

Looking ahead

The second phase of the T1 Parking Plaza is scheduled for completion in summer 2025, in time for the opening of 19 new gates as part of the terminal's redevelopment. The companies responsible for the design and construction of phase 1 are handling these same duties for phase 2.

 

“The opening of the first stage of the New T1 Parking Plaza represents more than just a milestone of the New T1 project, it represents significant progress toward providing our binational region with the air transportation infrastructure it needs and deserves,” said Gil Cabrera, the chair of the San Diego County Regional Airport Authority Board. “We can't wait to come back in the late summer of 2025 and cut the ribbon on the New T1.”

 

Michael Pendergrass is a principal at Watry Design, Inc. He can be reached at mpendergrass@watrydesign.com.

 

Project Credits

Owner: San Diego County Regional Airport Authority Board

Design-build contractor: Swinerton, Inc.

Architect and structural engineer of record: Watry Design, Inc.

Design architect: Gensler

Civil engineer: Latitude 33

Tags: ArchitectsConsultantsEnforcementEngineersEV ChargingFinancialGatedLicense Plate RecognitionLightingPaymentsPrivate Operators

parkingtodaystaff

Related Stories

Moving from Silos to Systems: The Case for Integrated Digital Parking Management

Moving from Silos to Systems: The Case for Integrated Digital Parking Management

by parkingtodaystaff
May 29, 2025

ADVERTORIAL by Mitch Carter As a parking operator, your business has always been about more than just spaces: It’s about...

A Garage that Shines

A Garage that Shines

by parkingtodaystaff
May 29, 2025

Sam Houston State’s newest garage is a model of smart lighting and user-focused innovation. By Anthony Sarti In fall 2024,...

Why I Love Parking

Why I Love Parking

by parkingtodaystaff
May 29, 2025

An architect’s unexpected journey into parking reveals how these structures affect daily urban life.By Eric Luttmann I never imagined that...

5 Digital Parking Pitfalls and How Smart Operators Avoid Them

5 Digital Parking Pitfalls and How Smart Operators Avoid Them

by parkingtodaystaff
May 29, 2025

Digital parking is here to stay, so avoid these five costly mistakes and stay ahead of the curve. By Dan...

Load More

Recommended

Editor’s Note … September 2024

September 1, 2024
Overcoming Obstacles On and Off the Lot

Overcoming Obstacles On and Off the Lot

March 1, 2025

Related Articles

5 Digital Parking Pitfalls and How Smart Operators Avoid Them
Commercial

5 Digital Parking Pitfalls and How Smart Operators Avoid Them

May 29, 2025
Artificial Intelligence and Parking: What the Public Thinks — And Why It Matters
Curb Management

Transforming Urban Curb Side Management: From Chaos to Efficiency

May 29, 2025
Moving from Silos to Systems: The Case for Integrated Digital Parking Management
Analytics

Moving from Silos to Systems: The Case for Integrated Digital Parking Management

May 29, 2025
Faith, Firewood, and Ingenuity on a Back Road
Analytics

Data Is Like a Matchbox Car Collection: Small Pieces, Big Potential

May 29, 2025
PIE at 25: Celebrating Connection, Community, and the Future of Parking
Consultants

Standards, Systems, and the Human Touch

May 29, 2025
Industry News … March 2025
Industry News

Industry News … June 2025

May 29, 2025
No Result
View All Result
Parking Today

Navigate Site

  • Advertise with Us
  • Contact
  • Privacy Policy

Follow Us

No Result
View All Result
  • Home
  • Park News
  • Buyer’s Guide
  • PIE Event Home
    • PIE 2026 Event
    • PIE 2025 Event
      • PIE25 Attendee Registration and Travel Details
      • PIE25 Agenda and Content Details
      • PIE25 Exhibitor & Sponsor Partnerships
      • PIE25 ParkFlix Film Festivial
      • Contact PIE25
  • Conference Companion
  • Segments
    • Higher Education
    • Municipal
    • Airport
    • Valet
    • Medical
    • Events
    • Commercial
    • Retail
    • Hospitality
  • Technologies
    • Gated
    • Ungated
    • Enforcement
    • Payments
    • Permits
    • Vehicle Detection
    • Wayfinding and Occupancy
    • Curb Management
    • Valet
    • Events
    • EV Charging
    • Analytics
    • Consumables
    • Lighting
  • Suppliers
    • Private Operators
    • Consultants
    • Engineers
    • Architects
    • Financial
    • Insurance
    • Mergers and Acquisitions
  • Industry Resources
    • Subscribe to Parking Today
    • Advertise with Us
    • Magazines
    • Industry Events
    • Conference Companion
    • Dealers, Installers & Suppliers – Listings
    • Industry News
    • Parking Jobs Network & RFP/RFQ’s
    • Associations
    • Podcast Network
    • Next Level – Webinar
    • Contact

Skip to content
Open toolbar Accessibility Tools

Accessibility Tools

  • Increase TextIncrease Text
  • Decrease TextDecrease Text
  • GrayscaleGrayscale
  • High ContrastHigh Contrast
  • Negative ContrastNegative Contrast
  • Light BackgroundLight Background
  • Links UnderlineLinks Underline
  • Readable FontReadable Font
  • Reset Reset